Hinkley Point C (£50m+)
- Provided full planning support including programme development, NEC compliance, progress tracking and delay analysis on a complex nuclear infrastructure project.
- The work required detailed integration of procurement, documentation and construction activities. A detailed programme was developed using experience and data from a comparable previous project, helping the delivery team identify key risks, opportunities and critical interfaces at an early stage.
- Ongoing planning advice supported the client in understanding programme risk, maintaining an accurate delivery position and developing Extension of Time submissions where required.
- Outcome: Improved programme accuracy, earlier identification of risk and a stronger basis for programme management and EOT negotiation.