Hinkley Point C (£50m+)

Case Study 01

Hinkley Point C (£50m+)

  • Provided full planning support including programme development, NEC compliance, progress tracking and delay analysis on a complex nuclear infrastructure project.
  • The work required detailed integration of procurement, documentation and construction activities. A detailed programme was developed using experience and data from a comparable previous project, helping the delivery team identify key risks, opportunities and critical interfaces at an early stage.
  • Ongoing planning advice supported the client in understanding programme risk, maintaining an accurate delivery position and developing Extension of Time submissions where required.
  • Outcome: Improved programme accuracy, earlier identification of risk and a stronger basis for programme management and EOT negotiation.

Norwich Castle- Delay

Castle

Norwich Castle- Delay Analysis

  • Provided specialist delay analysis services as part of a dispute resolution assignment relating to the Norwich Castle redevelopment project.
  • Outcome: Delivered a robust, evidence-based delay analysis that strengthened the client’s negotiating position, clarified responsibility for delay and supported the successful resolution of the dispute.

HMNB Devonport

9 Dock Devonport Construction

HMNB Devonport Dockyard – 9 Dock (£50m+)

      • Provided comprehensive planning, programme management and delay analysis support for a major NEC4 defence infrastructure package in South West England, valued at more than £50 million, from early project development through to practical completion.

      • The commission included early-stage quantities and take-offs, tender programme development and production of a compliant NEC4 Clause 31 baseline programme. Detailed programmes were developed from first principles for multiple work packages

      • Outcome: Delivered a robust contract-compliant programme through to practical completion, achieved regular programme acceptance, improved subcontractor coordination and strengthened the client’s position in delay negotiations.

    Power Generation

    Case Study 04

    Power Generation Projects – UK Wide

      • Provided planning, programme management and delay analysis support to one of the UK’s leading high-voltage specialist electrical engineering contractors, delivering power generation and high-voltage infrastructure projects across the UK.

      • Ongoing support included programme development, progress monitoring, critical-path review, delay analysis and advice on managing programme risk and contractual obligations.

      • Provide training to site teams. 